Brantas PSC
Gross production was 39.4 mmcfd. Strategic priorities for development
at Brantas include the optimization
of gas production from Wunut,
Tanggulangin and Carat gas fields,
new gas contracts and further
appraisal and exploration to realize
the potential of the deep Kujung
exploration play.
Six wells were spudded during the
year with success recorded in both
appraisal and development drilling.
Gas was found at the Tanggulangin-5
well, and both oil and gas found at
the Wunut-19 well. Tanggulangin first
gas is planned for the third quarter
of 2007, with 4 bcf sold at a contract
prices averaging US$ 4.1/mmbtu.
The
Carat field commenced gas production
in April 2006 at 2.5 mmcfd.
Banjarpanji well, spudded early in
2006, subsequently ceased operations
after substantial seismic activity in
Central Java during May.
|